Brisbane Airport Flight Path Changes Post Implementation Review
This project is closed.
Brisbane Airport’s new runway and the associated flight paths commenced operations on 12 July 2020. These flight paths have changed the way aircraft operate as they arrive and depart from Brisbane Airport.
Brisbane Airport Corporation and Airservices continue to work with stakeholders across community, government and industry to ensure that the Brisbane Airport operations meet the highest safety standards and incorporate the most environmentally sustainable practices wherever practicable.
For information on current aircraft operations visit our interactive Aircraft in Your Neighbourhood website here.
How do I receive updates on the PIR?
If you wish to receive further updates on the PIR, you must register and subscribe to follow this project.
Please also check in regularly for new information.
Brisbane Airport’s new runway and the associated flight paths commenced operations on 12 July 2020. These flight paths have changed the way aircraft operate as they arrive and depart from Brisbane Airport.
Brisbane Airport Corporation and Airservices continue to work with stakeholders across community, government and industry to ensure that the Brisbane Airport operations meet the highest safety standards and incorporate the most environmentally sustainable practices wherever practicable.
For information on current aircraft operations visit our interactive Aircraft in Your Neighbourhood website here.
How do I receive updates on the PIR?
If you wish to receive further updates on the PIR, you must register and subscribe to follow this project.
Please also check in regularly for new information.
-
CLOSED: This survey has concluded.
Please complete the below form to provide feedback on the Airservices PIR Draft Report.
This project is closed.
-
CLOSED: This survey has concluded.
You can provide feedback on Trax report and Airservices response by completing this form.
This project is closed.
-
Thank you for your interest in providing feedback on the following Noise Improvement Trials.
- Extension of Simultaneous Opposite Direction Parallel Runway Operations (SODPROPS) hours
- Restrictions on intersection departures from the New Parallel Runway
- QantasLink Dash 8 Q400 use of existing RNP-AR flight path over Moreton Bay
We recommend familiarising yourself with the factsheets on these trials prior to completing your survey response.
If you have specific questions or complaints about operations, please contact our Noise Complaints and Information Service (NCIS).
This project is closed.
-
CLOSED: This registration form is now closed.
Please register for workshop by completing this form.
This project is closed.
-
CLOSED: This survey has concluded.
Please complete this survey to help us ensure the workshop is focused on the recommendations from the Trax International report that are of greatest interest to the community, or on other areas of interest if not covered in the report.
This project is closed.
-
CLOSED: This survey has concluded.
This project is closed.
-
CLOSED: This registration survey has concluded.
Please complete this registration form to attend one of the Trax International Community Focus Groups.
This project is closed.
-
CLOSED: This survey has concluded.
Following the initial feedback period of the ToR, we have made changes to the draft and are now inviting further community feedback on the updated document.
To assist us in responding, please include reference to the section or page number of the report your comment is about.
The second draft of the ToR is available for comment from Monday 1 November to Sunday 21 November 2021 (midnight AEST)
This project is closed.
-
CLOSED: This survey has concluded.
We have developed draft Terms of Reference (ToR) which sets out our approach to undertaking the PIR. We have attempted to cover both our standard PIR requirements and also tailor some elements of the review to be specific to known community issues and interests.
To assist us in responding, please include reference to the section or page number of the report your comment is about.
The draft ToR is available for comment from Friday 30 July to Sunday 5 September 2021 (midnight AEST) and can be viewed here.
This project is closed.
-
CLOSED: This survey has concluded.
Thank you for registering your interest in attending the Samford Community Information session.
Due to COVID-19 restrictions in Brisbane affecting the number of people allowed in indoor venues, the community sessions have limited seating; however, the sessions will be Livestreamed and a recording of the sessions will be made available on the project Engage page.
This project is closed.
-
CLOSED: This survey has concluded.
Thank you for registering your interest in attending one of our sessions.
Due to COVID-19 restrictions in Brisbane affecting the number of people allowed in indoor venues, the community sessions are limited to 50 guests; however, the sessions will be Livestreamed and a recording of the sessions will be made available on the project Engage page.
To allow for equitable participation in the sessions and gathering of any data to support more detailed responses, we are asking for community questions be submitted by Wednesday 6 October. The opportunity to ask questions online and in person at the events will be provided, but responses may be limited by reasonable access to supporting information.
This project is closed.
-
CLOSED: This survey has concluded.
Thank you for your interest in the Brisbane PIR
To allow for equitable participation in the sessions and gathering of any data to support more detailed responses, we are asking for questions be submitted by Wednesday 13 October. The opportunity to ask questions online and in person at the events will be provided, but responses may be limited by reasonable access to supporting information.
This project is closed.
Timeline
-
July 2020
Brisbane Airport Flight Path Changes Post Implementation Review has finished this stageNew runway opened
-
July 2021
Brisbane Airport Flight Path Changes Post Implementation Review has finished this stagePost Implementation Review (PIR) commenced – Release of draft Terms of Reference
-
August 2021
Brisbane Airport Flight Path Changes Post Implementation Review has finished this stageModelled vs actual aircraft noise summary released
-
December 2021
Brisbane Airport Flight Path Changes Post Implementation Review has finished this stagePIR Terms of Reference finalised
-
December 2021
Brisbane Airport Flight Path Changes Post Implementation Review has finished this stageTrax International appointed to conduct independent review
-
February 2022
Brisbane Airport Flight Path Changes Post Implementation Review has finished this stageNoise improvement trials commenced
-
April 2022
Brisbane Airport Flight Path Changes Post Implementation Review has finished this stageTrax Interim Report released
-
July 2022
Brisbane Airport Flight Path Changes Post Implementation Review has finished this stageTrax Final Report received
-
August 2022
Brisbane Airport Flight Path Changes Post Implementation Review has finished this stageTrax Final Report released
-
August 2022
Brisbane Airport Flight Path Changes Post Implementation Review has finished this stageAirservices response to Trax Final Report
-
September 2022
Brisbane Airport Flight Path Changes Post Implementation Review has finished this stagePIR community workshops
-
October 2022
Brisbane Airport Flight Path Changes Post Implementation Review has finished this stageDraft PIR report released for public comment
-
October - November 2022
Brisbane Airport Flight Path Changes Post Implementation Review has finished this stagePublic comment period - closing 20 November 2022
-
December 2022
Brisbane Airport Flight Path Changes Post Implementation Review is currently at this stageFinal PIR report released
Documents
-
PIR report
- Brisbane Post Implementation Review - Final Report (1.1 MB) (pdf)
- Brisbane Post Implementation Review - Final Report Fact Sheet (1.19 MB) (pdf)
- Brisbane Draft PIR Report - Response to Feedback (1.43 MB) (pdf)
- Brisbane Post Implementation Review - Draft Report with tracked changes (1.04 MB) (pdf)
- Brisbane Post Implementation Review Report - Draft (1.02 MB) (pdf)
- Brisbane Post Implementation Review Report with appendices - Draft (20 MB) (pdf)
- Brisbane PIR Recommendations Community Workshops Slides (6.66 MB) (pdf)
- Trax International - Community Focus Groups Overview (344 KB) (pdf)
-
Noise Improvement Trials
- Noise Improvement Trial - Qlink RNP-AR 19L Over The Bay (294 KB) (pdf)
- Noise Improvement Trial - Intersection Departure Restrictions (298 KB) (pdf)
- Noise Improvement Trial - SODPROPS (160 KB) (pdf)
- Q1 - Brisbane Trial Results - Intersection Departures (1.02 MB) (pdf)
- Q1 - Brisbane Trial Results - SODPROPS (9.44 MB) (pdf)
- Q2 - Brisbane Trial Results - Intersection Departures (494 KB) (pdf)
- Q2 - Brisbane Trial Results - SODPROPS (563 KB) (pdf)
- Q3 - Brisbane Trial Results - Intersection Departures (516 KB) (pdf)
- Q3 - Brisbane Trial Results - SODPROPS (572 KB) (pdf)
- Q4 - Brisbane Trial Results - Intersection Departures (1.56 MB) (pdf)
- Q4 - Brisbane Trial Results - SODPROPS (1.38 MB) (pdf)
- PIR Factsheets
-
Brisbane PIR Terms of Referance
- Brisbane NPR PIR ToR_FINAL.pdf (513 KB) (pdf)
- Review_of_community_feedback__Draft_TOR_v0.2.pdf (827 KB) (pdf)
- BNE NPR PIR ToR_FINAL_changes tracked from v0.2 (2).pdf (368 KB) (pdf)
- BNE NPR PIR ToR_v0.2_for public comment_no markup.pdf (669 KB) (pdf)
- BNE NPR PIR ToR_v0.2_for public comment_mark-up.pdf (597 KB) (pdf)
- BNE NPR PIR ToR_v0.1 _Review of community feedback.pdf (1.14 MB) (pdf)
- PIR ToR v0.1 for public comment - July 2021 (521 KB) (pdf)
-
ToR Community Meetings
- Brisbane PIR Community Meetings (Nov 21)_Online Q&A.pdf (689 KB) (pdf)
- 23-10-21 community meeting - Brisbane PIR - Draft TOR Presentation.pdf (3.7 MB) (pdf)
- 18_10_21 - community meeting - Brisbane PIR Presentation (3.64 MB) (pdf)
- 15-10-21 community meeting - Brisbane PIR - Draft TOR presentation (3.65 MB) (pdf)
- 13-10-21 community meeting - Brisbane PIR - Draft TOR presentation (6.78 MB) (pdf)
- Brisbane Aiport runway operations optimisation and PIR (March 2021).pdf (378 KB) (pdf)
- PIR Factsheet - July 2021 (210 KB) (pdf)
Brisbane PIR FAQs
- What is the purpose of the PIR?
- What will be covered in the PIR?
- How long will the PIR process take?
- Why will the process take so long?
- Why are you doing a two phase PIR?
- Will the PIR redesign the flight paths?
- What capacity are the runways operating at currently?
- Will we have to wait up to 18 months for changes to be implemented?
- How can the community contribute to the Review?
- What are the main changes or alternatives that will be considered?
- How will the suggested alternatives be assessed?
- What are the different roles and responsibilities?
- Where can I find a copy of the Aircraft Noise Ombudsman Report on Brisbane flight path changes?