Hobart Community and Industry Suggested Alternatives
In April 2022, Airservices completed the Post Implementation Review (PIR) for the Hobart flight path changes that were implemented in November 2019. Airservices conducts PIRs into airspace and flight path changes to verify assumptions about potential environmental and community impacts and to determine the effectiveness of the environmental impact assessment and community engagement processes. The outcomes of PIRs inform future changes and improve the overall change management process.
The scope of the Hobart PIR was developed in consultation with the community and considered the supporting environmental assessments for the flight path changes, community information regarding aircraft operations and forecast noise, and flight path suggested alternatives from the community and industry.
The PIR identified an array of alternatives suggested by the community and industry, some of which were found to be viable for further investigation and detailed assessment. We have commenced detailed evaluation of these alternatives and have divided them into two packages of work.
Package 1 involves recommended action 5.
Package 2 includes recommended actions 4 and 6 -10.
A list of the recommended actions from the PIR is available here Hobart PIR Recommended Actions
In April 2022, Airservices completed the Post Implementation Review (PIR) for the Hobart flight path changes that were implemented in November 2019. Airservices conducts PIRs into airspace and flight path changes to verify assumptions about potential environmental and community impacts and to determine the effectiveness of the environmental impact assessment and community engagement processes. The outcomes of PIRs inform future changes and improve the overall change management process.
The scope of the Hobart PIR was developed in consultation with the community and considered the supporting environmental assessments for the flight path changes, community information regarding aircraft operations and forecast noise, and flight path suggested alternatives from the community and industry.
The PIR identified an array of alternatives suggested by the community and industry, some of which were found to be viable for further investigation and detailed assessment. We have commenced detailed evaluation of these alternatives and have divided them into two packages of work.
Package 1 involves recommended action 5.
Package 2 includes recommended actions 4 and 6 -10.
A list of the recommended actions from the PIR is available here Hobart PIR Recommended Actions
-
Recommendation 4 Assessment Outcome - Community Feedback
Thank you to all community members who provided feedback on Airservices’ Recommendation 4 assessment report and outcome. We appreciate the time taken to provide this feedback.
We received submissions from 47 individuals. 42 of these noted opposition to the decision, requesting it be reconsidered. Three submitters noted support and two did not state a specific position, providing more general feedback.
We have considered the feedback in detail, providing responses directly where questions were asked or clarification was sought. No feedback received has presented an issue not previously considered or a matter requiring further consideration and investigation that might require the original decision to be rejected.
As such, Airservices’ decision not to proceed with the relocation of the short approach to the east will remain unchanged. It was not considered reasonable to shift all southern runway end operations over the same area without the opportunity for respite.
The feedback received has led to some updates to the assessment report. This includes:
- Additional information in Section 2.2.2 explaining the two-kilometre corridor that is used for assessment of population directly overflown.
- Additional information in Section 2.2.3 explaining how community feedback informs the factors considered in assessments and why matters raised by communities are given regard in these assessments.
- Minor corrections to section references and caption numbers.
- Amendments to the size of the circles in Figure 11 to clarify that the area of cumulative impact does not include the area over water immediately south of these locations.
We received feedback questioning the inclusion of cumulative impact as a consideration in the assessment and stating that this information was not presented to the community during the engagement period, thereby not enabling community feedback on this matter. Assessment of the cumulative impact of the proposed change was in fact an outcome of the engagement. The subsequent assessment report review period has afforded the community the opportunity to review and provide feedback on this consideration. Had the information been supplied as part of initial materials presented during the engagement period, the opportunity for community feedback would be the same.
We also note receipt of feedback suggesting the assessment of Noise Abatement Procedure effectiveness should have been done prior to the last round of engagement. Airservices’ detailed assessment is conducted following community engagement on the preferred design to ensure all relevant factors are given regard to in this assessment. Airservices was committed to retaining this NAP given its success in reducing impacts on current short approach communities. Its effectiveness became more important following identification of the new areas of cumulative impact, as the ability to provide respite for these communities became a focus. The community was afforded the opportunity to review and provide feedback on this consideration as part of the assessment report review period.
Airservices acknowledges that not all community members are pleased with this outcome however, as stated in the assessment report, it was not deemed reasonable to remove all aircraft operations from one community, and to place them over another already subject to more operations in total and with no opportunity for respite.
This concludes Airservices’ investigation of the Post Implementation Review community suggested improvements.
We thank all communities for their active participation in this program.
Thank you to all community members who provided feedback on Airservices’ Recommendation 4 assessment report and outcome. We appreciate the time taken to provide this feedback.
We received submissions from 47 individuals. 42 of these noted opposition to the decision, requesting it be reconsidered. Three submitters noted support and two did not state a specific position, providing more general feedback.
We have considered the feedback in detail, providing responses directly where questions were asked or clarification was sought. No feedback received has presented an issue not previously considered or a matter requiring further consideration and investigation that might require the original decision to be rejected.
As such, Airservices’ decision not to proceed with the relocation of the short approach to the east will remain unchanged. It was not considered reasonable to shift all southern runway end operations over the same area without the opportunity for respite.
The feedback received has led to some updates to the assessment report. This includes:
- Additional information in Section 2.2.2 explaining the two-kilometre corridor that is used for assessment of population directly overflown.
- Additional information in Section 2.2.3 explaining how community feedback informs the factors considered in assessments and why matters raised by communities are given regard in these assessments.
- Minor corrections to section references and caption numbers.
- Amendments to the size of the circles in Figure 11 to clarify that the area of cumulative impact does not include the area over water immediately south of these locations.
We received feedback questioning the inclusion of cumulative impact as a consideration in the assessment and stating that this information was not presented to the community during the engagement period, thereby not enabling community feedback on this matter. Assessment of the cumulative impact of the proposed change was in fact an outcome of the engagement. The subsequent assessment report review period has afforded the community the opportunity to review and provide feedback on this consideration. Had the information been supplied as part of initial materials presented during the engagement period, the opportunity for community feedback would be the same.
We also note receipt of feedback suggesting the assessment of Noise Abatement Procedure effectiveness should have been done prior to the last round of engagement. Airservices’ detailed assessment is conducted following community engagement on the preferred design to ensure all relevant factors are given regard to in this assessment. Airservices was committed to retaining this NAP given its success in reducing impacts on current short approach communities. Its effectiveness became more important following identification of the new areas of cumulative impact, as the ability to provide respite for these communities became a focus. The community was afforded the opportunity to review and provide feedback on this consideration as part of the assessment report review period.
Airservices acknowledges that not all community members are pleased with this outcome however, as stated in the assessment report, it was not deemed reasonable to remove all aircraft operations from one community, and to place them over another already subject to more operations in total and with no opportunity for respite.
This concludes Airservices’ investigation of the Post Implementation Review community suggested improvements.
We thank all communities for their active participation in this program.
-
Feedback on Recommendation 4 Closed
The feedback period for Recommendation 4 Assessment Report has now closed. We acknowledge and thank community members for their engagement and feedback throughout this process. We are currently working through the feedback and will provide the outcome by the end of August 2026.
The feedback period for Recommendation 4 Assessment Report has now closed. We acknowledge and thank community members for their engagement and feedback throughout this process. We are currently working through the feedback and will provide the outcome by the end of August 2026.
-
Assessment Outcome – Recommendation 4 (Runway 30 short approach relocation)
Airservices Australia has completed its assessment of Recommendation 4 from the Hobart Post Implementation Review (PIR), which proposed relocating the Runway 30 (southern runway end) short approach (RNP‑AR) 2-3 kms to the east. This assessment has considered operational feasibility, safety requirements and community noise impacts, as well as feedback received from the community and industry.
The analysis identified that while the proposed relocation would reduce the number of people overflown in the current location, it would shift short approach operations to an area already affected by long approach arrivals and jet departures, increasing the cumulative noise burden. It also found that shifting the short approach would reduce the practical ability to share noise between arrival paths to provide periods of respite.
Based on the assessment, Airservices does not consider it reasonable to progress this suggested change through to implementation.
You can read the Preferred Option Assessment Summary here.
You can read the detailed Preferred Option Assessment Report here.
We recognise that this outcome will be disappointing for some members of the community, however where proposals present options that will shift operations to new areas, we must give full and proper regard to wide range of factors in making these complex decisions.
We invite questions and feedback on the assessment report until 16 August 2026.
Airservices Australia has completed its assessment of Recommendation 4 from the Hobart Post Implementation Review (PIR), which proposed relocating the Runway 30 (southern runway end) short approach (RNP‑AR) 2-3 kms to the east. This assessment has considered operational feasibility, safety requirements and community noise impacts, as well as feedback received from the community and industry.
The analysis identified that while the proposed relocation would reduce the number of people overflown in the current location, it would shift short approach operations to an area already affected by long approach arrivals and jet departures, increasing the cumulative noise burden. It also found that shifting the short approach would reduce the practical ability to share noise between arrival paths to provide periods of respite.
Based on the assessment, Airservices does not consider it reasonable to progress this suggested change through to implementation.
You can read the Preferred Option Assessment Summary here.
You can read the detailed Preferred Option Assessment Report here.
We recognise that this outcome will be disappointing for some members of the community, however where proposals present options that will shift operations to new areas, we must give full and proper regard to wide range of factors in making these complex decisions.
We invite questions and feedback on the assessment report until 16 August 2026.
-
Assessment Update - Recommendation 4
Thank you to all community members who provided feedback on the preferred option in relation to the suggested relocation further east of the short approach flight path to Hobart Airport's southern runway end. We are continuing to assess this option in response to the feedback received and expect to provide the outcome before the end of June 2026.
Thank you to all community members who provided feedback on the preferred option in relation to the suggested relocation further east of the short approach flight path to Hobart Airport's southern runway end. We are continuing to assess this option in response to the feedback received and expect to provide the outcome before the end of June 2026.
-
Recommendation 4 - Preferred design option assessment
The feedback period for the Recommendation 4 preferred design option is now closed. We will be completing the assessment of community and industry feedback in the coming weeks and will provide an update on our progress in Q1 of 2026. We expect to announce the outcomes of the assessment and if the recommendation will proceed to implementation in Q1/Q2, 2026.
The feedback period for the Recommendation 4 preferred design option is now closed. We will be completing the assessment of community and industry feedback in the coming weeks and will provide an update on our progress in Q1 of 2026. We expect to announce the outcomes of the assessment and if the recommendation will proceed to implementation in Q1/Q2, 2026.
-
Submit your feedback on Recommendation 4
It’s been 4 weeks since the feedback period commenced with the release of the Recommendation 4 fast sheet (available here).
If you have not already done so, we encourage community members to submit your feedback on Recommendation 4 and remember to give us your location when making your submission.
You can submit your feedback via communityengagement@airservicesaustralia.com until 11 January 2026.
It’s been 4 weeks since the feedback period commenced with the release of the Recommendation 4 fast sheet (available here).
If you have not already done so, we encourage community members to submit your feedback on Recommendation 4 and remember to give us your location when making your submission.
You can submit your feedback via communityengagement@airservicesaustralia.com until 11 January 2026.
-
Recommendation 4 - Environment Assessment released
We are pleased to release the Environment Assessment (EA) for Recommendation 4 of the Hobart PIR.
You can view the EA here.
Community engagement sessions will be held between 23 November and 25 November 2025 at Primrose Sands, Dodges Ferry and Dunalley. We invite you to come and discuss the preferred design option and speak with Airservices staff. Details of the sessions are available here.
You can provide feedback, ask questions and comment through to Sunday, 11 January 2026. Please click on the Questions tab to ask a question or provide feedback. You can also contact us at communityengagement@airservicesaustralia.com
We are pleased to release the Environment Assessment (EA) for Recommendation 4 of the Hobart PIR.
You can view the EA here.
Community engagement sessions will be held between 23 November and 25 November 2025 at Primrose Sands, Dodges Ferry and Dunalley. We invite you to come and discuss the preferred design option and speak with Airservices staff. Details of the sessions are available here.
You can provide feedback, ask questions and comment through to Sunday, 11 January 2026. Please click on the Questions tab to ask a question or provide feedback. You can also contact us at communityengagement@airservicesaustralia.com
-
Recommendation 4 Preferred Design Option - Fact Sheet Release
We are pleased to release the Preferred Design Option fact sheet for Recommendation 4 (Shift the Runway 30 RNP-AR 2 to 3km to the east) of the Hobart PIR.
You can view the fact sheet here.
A reminder that we will be holding community engagement sessions between 23 November and 25 November 2025 at Primrose Sands, Dodges Ferry and Dunalley. We invite you to come and discuss the preferred design option and speak with Airservices staff.
Details of the sessions are available here.
The Environmental Assessment (EA) for this preferred design will be available on this page in coming days. We will provide an alert to registered users once it is available.
You can provide feedback, ask questions and comment through to Sunday, 11 January 2026. Please click on the Questions tab to ask a question or provide feedback. You can also contact us at communityengagement@airservicesaustralia.com
We are pleased to release the Preferred Design Option fact sheet for Recommendation 4 (Shift the Runway 30 RNP-AR 2 to 3km to the east) of the Hobart PIR.
You can view the fact sheet here.
A reminder that we will be holding community engagement sessions between 23 November and 25 November 2025 at Primrose Sands, Dodges Ferry and Dunalley. We invite you to come and discuss the preferred design option and speak with Airservices staff.
Details of the sessions are available here.
The Environmental Assessment (EA) for this preferred design will be available on this page in coming days. We will provide an alert to registered users once it is available.
You can provide feedback, ask questions and comment through to Sunday, 11 January 2026. Please click on the Questions tab to ask a question or provide feedback. You can also contact us at communityengagement@airservicesaustralia.com
-
Recommendation 4 Community Engagement Sessions - Venues and times
We are pleased to announce the details of the upcoming community engagement sessions that will be held at Primrose Sands, Dodges Ferry and Dunalley. Come by anytime within the 2-hour time period to discuss the Preferred Design Option for Recommendation 4 of the Hobart PIR and speak to Airservices staff.
Details of the sessions are as follows:
Primrose Sands
Sunday 23 November, 1:30pm to 3:30pm
Primrose Sands Community Centre, 570 Primrose Sands Road, Primrose Sands
Dodges Ferry
Monday 24 November, 1:30pm to 3:30pm
Okines Community House, 540 Old Forcett Road, Dodges Ferry
Dunalley
Tuesday 25 November, 9.00am to11.00am
Dunalley Community Hall, 5 Franklin Street, Dunalley
If you are not able to attend an in-person session, you can submit a question using the Q&A function on this project page and we will get back to you.
We are pleased to announce the details of the upcoming community engagement sessions that will be held at Primrose Sands, Dodges Ferry and Dunalley. Come by anytime within the 2-hour time period to discuss the Preferred Design Option for Recommendation 4 of the Hobart PIR and speak to Airservices staff.
Details of the sessions are as follows:
Primrose Sands
Sunday 23 November, 1:30pm to 3:30pm
Primrose Sands Community Centre, 570 Primrose Sands Road, Primrose Sands
Dodges Ferry
Monday 24 November, 1:30pm to 3:30pm
Okines Community House, 540 Old Forcett Road, Dodges Ferry
Dunalley
Tuesday 25 November, 9.00am to11.00am
Dunalley Community Hall, 5 Franklin Street, Dunalley
If you are not able to attend an in-person session, you can submit a question using the Q&A function on this project page and we will get back to you.
-
Community Engagement Sessions - Preferred Design Option for Recommendation 4
We are pleased to announce that we will be holding community information sessions in the week commencing 23 November 2025.
The sessions are being held to discuss the outcomes of the Preferred Design Option assessment for Recommendation 4 of the Hobart Post Implementation Review (PIR). Details of the sessions will be released on this page in two weeks prior and the Fact Sheet will be released one week prior to the sessions commencing.
Follow this page for project updates.
We are pleased to announce that we will be holding community information sessions in the week commencing 23 November 2025.
The sessions are being held to discuss the outcomes of the Preferred Design Option assessment for Recommendation 4 of the Hobart Post Implementation Review (PIR). Details of the sessions will be released on this page in two weeks prior and the Fact Sheet will be released one week prior to the sessions commencing.
Follow this page for project updates.
-
Oct/Nov 2022
Hobart Community and Industry Suggested Alternatives has finished this stageCommunity engagement for Package 1
-
Nov 2022
Hobart Community and Industry Suggested Alternatives has finished this stageRelease of Noise Abatement Procedure options survey
-
Nov 2022
Hobart Community and Industry Suggested Alternatives has finished this stageOn-site community consultation sessions
Dodges Ferry: Monday 21 November from 4pm to 7pm (Okines Community House, 540 Old Forcett Road, Dodges Ferry)
Dunalley: Tuesday 22 November from 10am to 1pm (Dunalley Community Hall, 5 Franklin Street, Dunalley)
Primrose Sands: Tuesday 22 November from 4pm to 7pm (Primrose Sands RSL, 415 Primrose Sands Road, Primrose Sands)
Primrose Sands: Saturday 26 November from 10am to 3pm (Primrose Sands Community Centre, 570 Primrose Sands Road, Primrose Sands)
-
Nov 2022
Hobart Community and Industry Suggested Alternatives has finished this stageOnline community briefing session
Wednesday 23 November at 7pm
-
April/May 2024
Hobart Community and Industry Suggested Alternatives has finished this stageCommunity engagement on the operational requirements, exemptions and success criteria for a potential NAP trial
-
Mid-late 2024
Hobart Community and Industry Suggested Alternatives has finished this stageCommunity engagement on recommended actions 4 and 6 of the PIR
-
Early 2025
Hobart Community and Industry Suggested Alternatives has finished this stageAssessment of community and industry feedback for recommended actions 4 and 6 of the PIR
-
July 2025
Hobart Community and Industry Suggested Alternatives has finished this stageRelease of Options Assessment Outcomes - PIR Recommended actions 4 and 6
-
July 2025
Hobart Community and Industry Suggested Alternatives has finished this stageDevelopment of the preferred flight path design option - Recommendation 4
-
November 2025
Hobart Community and Industry Suggested Alternatives has finished this stageFact sheet and Environment Assessment (EA) for Recommendation 4 released
-
November 2025
Hobart Community and Industry Suggested Alternatives has finished this stageCommunity Information Sessions on Recommendation 4 - Preferred Design Option
-
Q1/Q2 2026
Hobart Community and Industry Suggested Alternatives is currently at this stageAssessment of community and industry feedback for recommended action 4 - preferred design option
-
Hobart Post Implementation Review Recommended Actions.pdf (420 KB) (pdf)
-
Recommendation 4 - RNP-AR relocation
-
Hobart Recommedation 4_Preferred Option Assessment Factsheet.pdf (2.89 MB) (pdf)
-
Recommendation 4 Preferred Option Assessment Report_Updated.pdf (4.07 MB) (pdf)
-
Hobart Rec 4 RNP-AR Preferred Design Option Fact Sheet.pdf (765 KB) (pdf)
-
Recommendation 4 Environment Assessment - Amendment to Runway 30 RNP-AR and visual approach (4.13 MB) (pdf)
-
Recommendation 4_Hobart RNP-AR Relocation (770 KB) (pdf)
-
Recommendation 4_Hobart RNP-AR Relocation_Noise Contours (579 KB) (pdf)
-
Recommendation 4 Options Assessment Report (1.86 MB) (pdf)
-
Recommendation 4 Options Assessment Summary (591 KB) (pdf)
-
-
Recommendation 5 - Noise Abatement Procedure
-
Recommendation 6 - East Coast Route
-
Community Motions
-
Hobart Rec 4_Preferred Option Assessment Factsheet.pdf (2.89 MB) (pdf)
-
Click here to play video A320 on RNAV approach to RWY 30 Noise levels associated with the movement of an A320 aircraft on the RNAV approach to RWY 30
-
Click here to play video B712 on RNAV approach to RWY 30 Noise levels associated with the movement of a B712 aircraft on the RNAV approach to RWY 30
-
Click here to play video B738 on RNAV approach to RWY 30 Noise levels associated with the movement of a B738 aircraft on the RNAV approach to RWY 30
-
Click here to play video A320 on RNP-AR approach to RWY 30 Noise levels associated with the movement of an A320 aircraft on the RNP-AR approach to RWY 30
-
Click here to play video B712 on RNP-AR approach to RWY 30 Noise levels associated with the movement of a B712 aircraft on the RNP-AR approach to RWY 30
-
Click here to play video B738 on RNP-AR approach to RWY 30 Noise levels associated with the movement of a B738 aircraft on the RNP-AR approach to RWY 30
-
Click here to play video A220 on RNAV approach to RWY 30 Noise levels associated with the movement of a A220 aircraft on the RNP-AR approach to RWY 30
-
Click here to play video A220 on RNP-AR approach to RWY 30 Noise levels associated with the movement of a A220 aircraft on the RNP-AR approach to RWY 30
-
Click here to play video A220 on proposed RNP-AR approach to RWY 30 Noise levels associated with the movement of a A220 aircraft on the proposed RNP-AR approach to RWY 30
-
Click here to play video A320 on proposed RNP-AR approach to RWY 30 Noise levels associated with the movement of an A320 aircraft on the proposed RNP-AR approach to RWY 30