Hobart Community and Industry Suggested Alternatives
In April 2022, Airservices completed the Post Implementation Review (PIR) for the Hobart flight path changes that were implemented in November 2019. Airservices conducts PIRs into airspace and flight path changes to verify assumptions about potential environmental and community impacts and to determine the effectiveness of the environmental impact assessment and community engagement processes. The outcomes of PIRs inform future changes and improve the overall change management process.
The scope of the Hobart PIR was developed in consultation with the community and considered the supporting environmental assessments for the flight path changes, community information regarding aircraft operations and forecast noise, and flight path suggested alternatives from the community and industry.
The PIR identified an array of alternatives suggested by the community and industry, some of which were found to be viable for further investigation and detailed assessment. We have commenced detailed evaluation of these alternatives and have divided them into two packages of work.
Package 1 involves recommended action 5.
Package 2 includes recommended actions 4 and 6 -10.
A list of the recommended actions from the PIR is available here Hobart PIR Recommended Actions
In April 2022, Airservices completed the Post Implementation Review (PIR) for the Hobart flight path changes that were implemented in November 2019. Airservices conducts PIRs into airspace and flight path changes to verify assumptions about potential environmental and community impacts and to determine the effectiveness of the environmental impact assessment and community engagement processes. The outcomes of PIRs inform future changes and improve the overall change management process.
The scope of the Hobart PIR was developed in consultation with the community and considered the supporting environmental assessments for the flight path changes, community information regarding aircraft operations and forecast noise, and flight path suggested alternatives from the community and industry.
The PIR identified an array of alternatives suggested by the community and industry, some of which were found to be viable for further investigation and detailed assessment. We have commenced detailed evaluation of these alternatives and have divided them into two packages of work.
Package 1 involves recommended action 5.
Package 2 includes recommended actions 4 and 6 -10.
A list of the recommended actions from the PIR is available here Hobart PIR Recommended Actions
-
Recommendation 4 & 6 - Design Option Fact Sheets
We are pleased to release information for Recommendation 4 & 6 of the Hobart PIR.
We will be holding a series of on-site and an online community engagement session, details of which are in the newsfeed below. Feedback from the community is encouraged. You can view the Fact sheets using the links below.
- Recommendation 4_Hobart RNP-AR Relocation
- Recommendation 4_Hobart RNP-AR Relocation Noise Contours
- Recommendation 6_Hobart East Coast Route Suggestion
- Recommendation 6_Hobart East Coast Route Suggestion_FPDP
We invite you to submit feedback via the 'Have Your Say' tab on this page or alternatively, you can provide your feedback for Recommendation 4 here and Recommendation 6 Recommended action 6 here.
-
Community engagement sessions – Post Implementation Review Recommendation 4 and 6
Airservices has now completed the assessment of Recommendations 4 and 6 from the Hobart Airspace Design Post Implementation Review. We will be holding face-to-face community engagement sessions commencing 12 November 2024 to discuss the outcomes of the assessments. Community sessions will be held at Dodges Ferry, Primrose Sands, Dunalley and Triabunna. These will be drop-in style sessions where community members can have one-on-one and small group conversations with Airservices staff to further understand the outcomes of this work.
Details of the sessions are as follows:
Tuesday 12 November, 1:30pm to 3:30pm
Dodges Ferry
Okines Community House, 540 Old Forcett Road, Dodges Ferry
Tuesday 12 November, 5.00pm to 7.00pm
Primrose Sands
Primrose Sands Community Centre, 570 Primrose Sands Road, Primrose Sands
Wednesday 13 November, 5.00pm to 7.00pm
Dunalley
Dunalley Community Hall, 5 Franklin Street, Dunalley
Thursday 14 November, 11:30am to 1:30pm
Triabunna
Triabunna Community Centre, 3 Vicary St, Triabunna
Anyone who is unable to attend the in-person sessions is welcome to register to attend an online session, which will involve a short presentation followed by questions.
Wednesday 20 November, 12:00pm to 1:00pm
Online Session - Click here to register
Information on the two recommendations will shared on this page next week.
Noise Abatement Procedure (NAP) trial update
Airservices has reviewed the operation of the trial over its first 3 months.
Between 13 June 2024 and 12 September 2024, there were 1851 arrivals to runway 30. Of these:
• 42 percent used the shorter RNP-AR approach
• 58 percent used the longer RNAV approach.
This result is within the desired success criteria for the trial, and points to its success in better sharing operations between these two arrival paths.
We also looked into adherence with the NAP during the prescribed hours, and identified:
• Two flights were instructed by air traffic control to use the RNP-AR due to emergency services aircraft activity
• One aircraft used the RNP-AR to avoid bad weather
• One aircraft used the RNP-AR outside of tower hours
• Six pilots requested the RNP-AR approach for operational reasons.
Airservices has contacted the relevant airlines to understand the operational reasons for not adhering to the NAP and to encourage use where operationally safe.
Your ongoing feedback will be a key consideration in the assessment of this trial and you can submit your feedback on the NAP trial through our online form available here.
Members of the community are welcome to discuss the details of the NAP trial with our staff at the upcoming engagement sessions.
-
Update on community suggested alternatives 4 and 6
Airservices has completed assessment of the community suggested recommendations, number 4 and 6, from the Hobart Airspace Review Post Implementation Review (PIR). We are now preparing the relevant information to share with the community on these recommendations and other Hobart operations, including an update on the progress of the Noise Abatement Procedure (NAP) trial. We anticipate commencing face-to-face community engagement sessions from mid-October 2024.
In the meantime, we encourage community members to continue providing feedback on the NAP trial through our online form available here. Your feedback will be a key consideration in the assessment of this trial.
-
Update on PIR recommended actions
Airservices will soon announce the next round of community engagement on the recommendations of the Hobart Airspace Review Post Implementation Review (PIR). We are currently finalising our assessment of the options and anticipate being able to confirm the engagement timing in the next month. In the meantime, we encourage any community members with feedback on the Noise Abatement Procedure (NAP) trial, to record your feedback here.
.
-
Runway 30 NAP Trial Implementation
Airservices has completed community and industry engagement on the additional work requested by our CEO for the Noise Abatement Procedure (NAP) Trial. This involved operational safety assessment, including exclusions and exemptions to its use, and the criteria against which the NAP trial success or otherwise will be measured. The assessment found no reason that we should not proceed with the NAP trial, in accordance with the original recommendation from August 2023.
The completion of this additional work was necessary to confirm if any safety risks posed by this change in operations can be mitigated. It also provided the opportunity to further explain when aircraft are not required to apply the NAP and to share our proposed approach to monitoring and measuring the trial’s success.
The NAP trial will commence on 13 June 2024 and will be in effect for a period of 6 months.
Over this period, arriving aircraft to runway 30 will use the RNAV approach (also known as the long approach) between the hours of 2pm and 8am, unless they are exempt for specific reasons. Details on the conditions for exemptions are available here.
Feedback from the community and industry gathered throughout the trial period will inform our assessment of the trial. Members of the public are encouraged to submit feedback via the Have Your Say tab on this page.
We are also currently installing noise monitors in key locations identified by our specialist aircraft noise monitoring consultants to record noise levels throughout the trial. These have been placed at:
- Primrose Sands – to monitor arrivals to runway 30 on the RNP-AR/visual arrival route (short approach)
- Connelly’s Marsh – to monitor arrivals to runway 30 on the RNAV arrival route (long approach) and jet departures from runway 12.
We are also seeking to deploy a noise monitor in the vicinity of Dunalley to monitor overflight in this location. We invite members of the community to contact us at communityengagement@airservicesaustralia.com if you are interested in hosting a noise monitor (noting the location selected will need to meet the required noise monitoring criteria).
Hobart Airport runway works
We have recently become aware that Hobart Airport is planning to commence upgrade works to the runway. We do not expect these works to impact the trial however we are currently working with the airport to understand any changes to existing operations and will provide updates as we learn more.
-
Runway 30 NAP trial operational safety assessment
We have now completed additional detailed operational safety work to more fully understand any risk associated with the proposed NAP trial engaged on in 2023, as well as looking at exclusions and exemptions to its use, and the criteria against which its success or otherwise could be measured.
We have finalised this assessment, which has confirmed that the NAP trial can be safely implemented with appropriate controls, exclusions and exemptions.
With these safety elements now confirmed, the NAP trial will be implemented for a period of 6 months commencing in mid-June 2024.
The proposed NAP would operate between 2pm and 8am, with all arrivals to runway 30 using the RNAV (longer approach) during these hours, excluding valid exemptions.
Further details can be viewed here.
Members of the community are welcome to discuss the details of the NAP trial with our staff at next week’s community sessions. Dates, times and venues are listed in the previous update on this page.
-
Update on the NAP trial
Following the review of our NAP trial assessment decision, we have completed the additional work we committed to, including operational safety assessment, identifying exclusions and exemptions to NAP use and also the criteria to measure success.
After the school holidays we will be hosting a series of community sessions at Dodges Ferry, Dunalley and Primrose Sands. These will be drop-in style sessions where community members can have one-on-one conversations with Airservices staff to further understand the outcomes of this work.
MONDAY 29 APRIL, FROM 4.30PM TO 7.30PM
DODGES FERRY
Okines Community House, 540 Old Forcett Road, Dodges Ferry
TUESDAY 30 APRIL, FROM 4.30PM TO 7.30PM
PRIMROSE SANDS
Primrose Sands Community Centre, 570 Primrose Sands Road, Primrose Sands
WEDNESDAY 1 MAY, FROM 4.30PM TO 7.30PM
DUNALLEY
Dunalley Community Hall, 5 Franklin Street, Dunalley
Anyone who is unable to attend the in-person sessions is welcome to register to attend an online session, which will involve a short presentation followed by questions.
SATURDAY 4 MAY, FROM 3.30PM TO 5.00PM - Click here to register
Information on the outcomes of this additional work will be shared on this page approximately one week prior to the first community information session.
We acknowledge this is in the school holiday period and we do not expect any immediate response from the community.
Our four week engagement period will commence after the completion of the holidays.
-
Review of Runway 30 NAP trial assessment outcome
In August we published our decision to not proceed with the proposed Noise Abatement Procedure (NAP) trial for Runway 30 at Hobart Airport. The Aircraft Noise Ombudsman (ANO) reviewed this decision and has since requested that Airservices Australia reconsider this outcome.
Airservices’ Chief Executive Officer completed a review of the decision, and he has requested that further work be completed to determine if the NAP trial should be implemented.
This work includes:
• additional engagement with community and industry on the operational requirements and exemptions to the NAP, along with the success criteria that would be applied to the NAP trial, should it be implemented
• assessment of the safety and operational factors to be considered should a NAP trial be implemented, including determining if the risks are acceptable following applicable mitigations.
The safety assessment work will be undertaken in parallel to industry engagement. We will then engage with the community on the outcomes.
We anticipate engaging with the Hobart community in early 2024.
Work is currently underway on the recommended actions in Package 2. We expect to commence engagement with the Hobart community on these proposals at the same time as the above.
-
Outcome of the Noise Abatement Procedure Trial Assessment
Assessment of the proposed Noise Abatement Procedure (NAP) trial has now been completed and the decision has been made not to proceed with the trial.
Feedback from the community was almost evenly divided between those who supported a trial and those who did not. To further assess the merit of the trial, we undertook a detailed assessment of each option using our Flight Path Design Principles, which having first given regard to safety, require a careful balance of operational efficiency, protecting the environment and minimising the effects of aviation noise on the community.
The outcome of this assessment concluded that implementation of the NAP trial rated slightly higher than to not proceed with the trial. Given diverting all air traffic during the NAP period to the longer approach would result in a considerable amount of additional CO2 emissions, a higher degree of community benefit and community support for the change is required to justify its implementation.
We understand that this decision will come as a disappointment to some members of the community, however changes to air traffic control operational procedures are complex and require a compelling case to do so.
The details of the Noise Abatement Procedure Trial assessment are available here.
We propose to host community information sessions to discuss the outcomes of the NAP trial assessment. These will take place in the areas of Dodges Ferry, Primrose Sands and Dunalley in the coming weeks. The dates, times and venues for these sessions will be advised on this page and will be advertised locally. You are encouraged to subscribe to receive updates.
Further work is currently being undertaken on recommended actions 4 and 6-10 of the Hobart Airspace Review Post Implementation Review. Updates on this work will be published on this page as the work progresses together with the opportunity to provide feedback.
-
Noise Abatement Procedure Trial Assessment
We have been undertaking a thorough assessment of the proposed Noise Abatement Procedure Trial, giving careful consideration to each of our Flight Path Design Principles. We have completed the assessment and will be releasing a decision shortly.
We understand that the community are keen to see a resolution of this issue and we thank you for your patience.
Follow Project
Timeline
-
Oct/Nov 2022
Hobart Community and Industry Suggested Alternatives has finished this stageCommunity engagement for Package 1
-
Nov 2022
Hobart Community and Industry Suggested Alternatives has finished this stageRelease of Noise Abatement Procedure options survey
-
Nov 2022
Hobart Community and Industry Suggested Alternatives has finished this stageOn-site community consultation sessions
Dodges Ferry: Monday 21 November from 4pm to 7pm (Okines Community House, 540 Old Forcett Road, Dodges Ferry)
Dunalley: Tuesday 22 November from 10am to 1pm (Dunalley Community Hall, 5 Franklin Street, Dunalley)
Primrose Sands: Tuesday 22 November from 4pm to 7pm (Primrose Sands RSL, 415 Primrose Sands Road, Primrose Sands)
Primrose Sands: Saturday 26 November from 10am to 3pm (Primrose Sands Community Centre, 570 Primrose Sands Road, Primrose Sands)
-
Nov 2022
Hobart Community and Industry Suggested Alternatives has finished this stageOnline community briefing session
Wednesday 23 November at 7pm
-
April/May 2024
Hobart Community and Industry Suggested Alternatives has finished this stageCommunity engagement on the operational requirements, exemptions and success criteria for a potential NAP trial
-
Mid-late 2024
Hobart Community and Industry Suggested Alternatives is currently at this stageCommunity engagement on recommended actions 4 and 6 of the PIR
Documents
- NAPS fact sheet (1.46 MB) (pdf)
- HBA NAP trial assessment decision.pdf (5.44 MB) (pdf)
- NAP implementation fact sheet (562 KB) (pdf)
- Hobart Post Implementation Review Recommended Actions.pdf (420 KB) (pdf)
- Recommendation 6_Hobart East Coast Route Suggestion (847 KB) (pdf)
- Recommendation 6_Hobart East Coast Route Suggestion_FPDP Assessment (587 KB) (pdf)
- Recommendation 4_Hobart RNP-AR Relocation (770 KB) (pdf)
- Recommendation 4_Hobart RNP-AR Relocation_Noise Contours (579 KB) (pdf)
- Hobart - Post Implementation Review - Final Report.pdf (28.3 MB) (pdf)
Videos: noise levels
- Noise levels associated with the movement of an A320 aircraft on the RNAV approach to RWY 30
- Noise levels associated with the movement of a B712 aircraft on the RNAV approach to RWY 30
- Noise levels associated with the movement of a B738 aircraft on the RNAV approach to RWY 30
- Noise levels associated with the movement of an A320 aircraft on the RNP-AR approach to RWY 30
- Noise levels associated with the movement of a B712 aircraft on the RNP-AR approach to RWY 30
- Noise levels associated with the movement of a B738 aircraft on the RNP-AR approach to RWY 30